Sunday, 5 November 2017

The snow

It came before we had the roof of the scaffolding on. But thats ok, it is gone already! So we had snow for a week. We didnt do much (work related) during that time but now that the snow is gone we will really go at it for this coming week and try to get as much as possible done before it snows again.



The King post trusses are up (the large A shape on the top). That we had done before the snow came. We prepared the trusses on the floor by making the joints and drilling the holes for the screws. So basically we put them together and then took them apart. Then we lifted the logs one by one up with a winch and Mick put the trusses back together again on the top. Then we lifted each king post truss up to the right position with ropes and winches and four persons. There goes a ridge beam on top of the trusses and there will come another one of them next week.  

Tuesday, 17 October 2017

Views from above

 North
On the left: logs waiting to go up for the roof of the scaffolding. 
On the right: kids having a snack. And roof tins waiting.
In the middle: the very end of our road. We don't intend it to come to our house once the house is ready
Middle behind: under rusty roof tins posts and beams for the house (to be used next after the scaffolding and temporary roof is ready)

West
The top of the scaffolding, about 6.1 meters above the ground.
On this we will now start building the roof of the scaffolding for us to be able to work longer into autumn and eventually we can build the roof of the house under the roof of the scaffolding.
A big benefit of Mick being a rock climber is that he is able to walk and work up here! He might be the only one who can...

The top of the scaffolding from below
Mick put the boards every 60cm (2 feet) for him to feel safe to walk and work up there

Saturday, 14 October 2017

6th of July 2017 till 6th of October 2017

        
6.7.2017
Site cleared from trees

6.10.2017
Foundation done, joists done, scaffolding half done

Tuesday, 3 October 2017

Scaffolding


When the floor beams were ready with the mortise and tennon joints we put down 32 8x2 floor joists all around the house. This really changed the feeling of the area! The leca foundation and the joints of the beams are covered from the rain with some roof tin Mick collected for free from Joensuu. Every morning when we start work we need to take the covers off.

Having lunch

Now we started building a scaffolding for the house. It will have a roof on it so the whole house will be covered until it has its own roof on. This way we can work in the rain, we can work later into the autumn/winter and we dont need to uncover and cover everything when we come to work and leave work. The scaffolding/temporary rain cover is built from our peeled spruce posts and boards. It took some practice and strength to get them 12 posts into place but we got really good and fast at it and we got the last post in place just before our last helper left.

Luckily Mick is not scared of heights

All the posts are connected to each other with boards. On top of the boards there are planks to walk on. This will still get a third level on it and more support boards and planks to walk on. We ran out of the boards we had the saw mill make for us (of this size) so now we are using used boards we collected last week from near Joensuu for free. They are full of nails so we first need to de-nail them. I do the de-nailing while Mick is up high building.

Wednesday, 27 September 2017

Mortise and tennon joints

These are a few things we have done with the help of our helpers during the last month and a half.



We dug a ditch to direct the water away from the road/yard. 


The gravel from the digging we placed under our house so between the big rocks and towards the middle foundation. The gravel was placed there to make the ground higher and make it slope away from the house so that all the water from the rain and melting snow do not go under the house. We needed more gravel than from the ditch so we dug that from the edge of the forest. Also we placed stones in cement on top of the foundation rocks to make them all the same hight and even.


Then we began the carpentry work. We got our nine beams that were cut square by the mobile saw mill in the winter.
These floor beams were joined with a halving joints that were made with a motor saw, axe and chisel.


At each of these joints there is a mortice and tennon joint which is the junction between the wall posts and the floor beams. This also fixes the beams together. 
The beams are placed on birch bark to stop the moisture from traveling from the stone to the beam. The  surface of the beam was burned with a blow torch to dry the wood to paint it with wood tar. The tar works against insects who don't like the tar (nor the charring).  


The 4x2inch mortise joint was made by hand drilling eight one inch holes to make the chiseling easier.


Each beam is bolted onto the rock at the point of the mortise joint. This stops any possible movement of the house.


The whole family chiseling (in a local news paper article).
"Itse rakentaen kodilla on sielu - by building yourself your house has a soul"

Monday, 28 August 2017

Bark art by beetle worms

A peeling from spruce bark. The figure(s) are made by bugs. Peeled and found by David, one of our helpers. How many faces do you find?

Friday, 4 August 2017

Building the foundation


Filling the hole with stones

So after the digger came and put the foundation rocks in place we have started building the foundation for the chimney, oven, stove and an interior cob wall. The area is about 7m2. The digger dug a huge hole and it was filled with stones called anti capillary stones. They prevent the frost from moving the foundation/house because the dampness does not stay in the stones so they cant have frost in them either. The stones were compacted with a wacker, then covered with fine sand that was compacted and leveled.

Tying the reinforcing bars

On the sand we put 50mm load bearing insulation boards and built a timber shutter to hold the concrete foundation, we put in steel reinforcing bars to strengthen the concrete which we mixed on site using a petrol powered cement mixer. This is the only place we will have concrete in our house.
The wooden shutter was removed and then we started building the insulating leca (light weight expanded clay aggregate) bricks up. At the same time we have built a deep box (at right in pic. above) to bring three pipes up into the house. One pipe for water coming in, one for waste water going out and one pipe for an electricity cable. The box is also insulated.

Dry testing the leca bricks to see how they fit best

Laying leca bricks

We have a cement mixer that was shipped from Ireland amongst all the other tools that Mick had there. We also have a petrol generator to make electricity for cutting the bricks and using other power tools.
All the building materials we need to buy we can buy from Joensuu thats about 20km away. We are lucky to have a use of my dads van to transport bigger stuff.

Today we completed laying the leca bricks for the chimney, oven, wood cooking stove and cob wall base. Next week we get to start the carpentry work! We, specially Mick has really been waiting for that. And it is August already...